Smart-ready service C-2b · Cooling
Sequencing of different cooling generators
In short
- 1This service has 5 levels, from manual to fully automatic.
- 2Priorities only based on running times → Sequencing based on dynamic priority list, including external signals from grid.
- 3This service is only part of the full Method B.
The levels
Level 0
Priorities only based on running times
Level 1
Fixed sequencing based on loads only: e.g. depending on the generators characteristics such as absorption chiller vs. centrifugal chiller
Level 2
Dynamic priorities based on generator efficiency and characteristics (e.g. availability of free cooling)
Level 3
Load prediction based sequencing: the sequence is based on e.g. COP and available power of a device and the predicted required power
Level 4
Sequencing based on dynamic priority list, including external signals from grid
Relevant for these building types
Next step